Sunday 28 June 2015

Retaining wall

Couldn't believe trades were on site on a Sunday!... but retaining wall's looking good...






Thursday 25 June 2015

Week 4 - frame's done!

Estimated timeframe for frame stage: 4-6 weeks... actual completion of frame stage: less than 2 weeks!!

Ground floor & first floor frame and upper storey roof trusses all done! Next stage: lock up... we know things will slow down a little from now but are confident Carter Grange will keep it up ☺




Saturday 20 June 2015

Week 3 - taking shape

Another very productive week, and quite impressed at how much Carter Grange's carpenter Mark and his team have achieved in just 6 days (yes, they were on site Saturday)... the house is now taking shape with the ground floor frame, steel beams, ground-first floor cover and front part/facade of the first floor frame done.

... to Saturday afternoon


from Monday morning...

Thursday 11 June 2015

Week 2 - we have a slab!

Estimated timeframe for base stage: 4-6 weeks... actual completion of base stage: 2 weeks!!

Form work and concrete pour all done in 3 days!... and yes, we have a slab ☺ very impressed Carter Grange

Friday 5 June 2015

Week 1 - site's ready

Happy to say that trades have been on site pretty much every day including Saturday, and happy to see the progress... looks like all underground drains, plumbing & slab piers are done, and we have a meter box! Keep up the good work Carter Grange ☺