Thursday 25 June 2015

Week 4 - frame's done!

Estimated timeframe for frame stage: 4-6 weeks... actual completion of frame stage: less than 2 weeks!!

Ground floor & first floor frame and upper storey roof trusses all done! Next stage: lock up... we know things will slow down a little from now but are confident Carter Grange will keep it up ☺