Tuesday 15 September 2015

Pre-plaster re-inspection

As arranged, we met again with our SS on site this morning to check off the pre-plaster items. The carpenters were also on site fixing/finishing off anything outstanding, and happy to report that:

● bed 2 external wall was being leveled
● the stairs dwarf wall had been leveled
● the tie-down bracings were tight
● the heating unit had been relocated over the load trusses
● gaps to the window & door were properly insulated
● the ensuite & ground floor wet spots appeared to be dry, and as I dropped by this arvo noticed the roof guy up there replacing the missing tiles

We also went over some of the other esthetics & external items in the report, and were reassured that these would be addressed in due course, so we'll have to wait and see.

As the inspector said no building project goes without any issues (big or small) and that you simply want the builder to respond, address and/or fix them, which so far Carter Grange have done.

Our SS also said that the plastering was scheduled to start tomorrow, and that he expects the fixing stage to be done by end Sep-early Oct!

Certainly can't complain about the progress so far ☺