Saturday 3 October 2015

Week 18 - fixing stage done :)

Eventually managed to get a sneak peek yesterday, but it wasn't until late afternoon coz of all days couldn't believe the renderers were actually on site working on a public holiday!... certainly cannot complain about Carter Grange keeping up with the progress.

So far so good, except for the kitchen pot drawers which somehow the cabinet maker got wrong :/ basically the middle ones are too small & the bottom ones too big, but we're meeting with our SS on site this Tuesday morning to sort it out.

Otherwise, all plastered walls prepped & ready for painting, all internal doors (excl. cavity & robe sliding doors) are in, all cupboards & cabinetry (except for laundry most likely happening on Monday) are installed and we've finally got stairs!... so no more climbing up & down the ladder.

With the completion stage, which can take up to 10 weeks, starting next week and provided the kitchen drawers can be fixed quickly, here's hoping for a pre-xmas delivery! ☺

Stairs

Kitchen




Butler's Pantry

Ensuite cabinets
Bathroom cabinets

Entry

Dining-Kitchen

Dining-Living

Leisure-Balcony


Leisure-Stairs


WIR

No comments:

Post a Comment