Friday 30 October 2015

Week 22 - we're getting there

We can't believe it's been just 5 months since Carter Grange started our build...

The update is painting's done (save for final touches at the end), electricals are done, heat/cool vents and thermostats are done, waterproofing's done, kitchen drawers being replaced as we speak, handles on internal and front doors installed so no more sneaking in :/ and the ground floor external rendering has resumed.

Next is our pre-tiling inspection of the waterproofing first thing Wednesday morning, followed of course by the tiling... and then it's mainly the stone benchtops, built-in robes and flooring!

So we can almost see the finish line now, it's all very exciting, and a bit daunting as we're starting to look at furniture, much sooner than expected... keep you posted :)